How to Enable Auto-Shift Planning

Auto-shift planning decides how a project reacts when a task's dates change and other tasks depend on it: shift everything downstream automatically, or just get warned about the overlap.

Why Is This Feature Included?

Moving one task's dates can leave its dependents out of sync — a successor left starting before its predecessor finishes, for example. Auto-shift planning lets you choose whether Taskip fixes that for you automatically, or simply flags it so you can decide.

Where to Find It

  1. Open the project and go to its Settings tab.
  2. Select the Planning section.

The Setting

Shift dependent tasks automatically — off by default.

  • Off: if moving a task's dates would now overlap a dependent, you get an info toast explaining the overlap, with a link back to this setting. Nothing is changed for you.
  • On: when a task's dates move, everything that depends on it moves too, following the relationship type:
    • A Finish to start dependent is pushed to start after its predecessor now finishes.
    • A Start to start dependent is dragged to start alongside its predecessor.
    • A Finish to finish dependent is kept level with its predecessor's finish date.

Shifting only ever moves a dependent's dates forward or backward to stay in sync — a task's own duration doesn't change, and tasks already in a Done stage are never moved. Shifts propagate through the whole chain: if C depends on B and B depends on A, moving A can shift both B and C.

What You'll See

  • Turning the setting on and moving a predecessor's dates shows a toast confirming how many dependent tasks moved.
  • Each shifted task's activity history records that it moved because a predecessor's dates changed.
  • On the Gantt view, shifted dependency links update immediately.

Saving

Toggle the switch, then click Save on the Planning section to apply it.