Task dependencies let you link tasks in the same project so Taskip can tell you when one is waiting on another — and, if you turn on auto-shift planning, keep their dates in sync automatically.
Dependency Types
When you link two tasks, you choose how they relate:
- Finish to start — the second task can't finish until the first one is done. This is the most common type.
- Start to start — the two tasks are meant to start together.
- Finish to finish — the two tasks are meant to wrap up together.
You can also add an optional lag (days) — extra time to leave between the two tasks beyond the relationship itself.
Where to Manage Dependencies
- Open a task's detail view.
- Go to the Dependencies section.
You'll see two lists:
- Blocked by — tasks this one depends on (its predecessors).
- Blocks — tasks that depend on this one (its dependents).
Adding a Dependency
- In the Dependencies section, click Add dependency.
- Search for and select the task this one depends on.
- Choose the relationship type (Finish to start / Start to start / Finish to finish).
- Optionally set a lag in days.
- Click Add dependency to save.
Dependencies can only be made between tasks in the same project, and Taskip won't let you create a loop — if a link would create a cycle (for example, A depends on B, and you try to make B depend on A), the request is refused with an error.
What "Blocked" Means
A task is marked Blocked when a predecessor hasn't reached the stage the relationship requires:
- A Finish to start predecessor that isn't yet in a Done-category stage.
- A Start to start predecessor that's still in Backlog or To Do.
- A Finish to finish predecessor that isn't Done while this task already is.
Blocked status is computed live from your board — you never set it by hand.
Finding Blocked Work
- A Blocked badge appears on task cards and rows across the board and list views.
- Use the Blocked filter on the board to show only blocked tasks.
Removing a Dependency
Open the task's Dependencies section and remove the link from either the Blocked by or Blocks list. Removing a dependency doesn't change either task's dates.
Related
- How to Enable Auto-Shift Planning — automatically move dependent tasks' dates when a predecessor's dates change.
- How to Use the Gantt View — see dependency links drawn between tasks on the timeline.
- How to Use Milestones